Friday, November 30, 2012

Roof Frame complete

It took longer than I expected, but the roof frame is complete and some finishing touches the house frame are also done. Electric cables have been placed for all light and power points.
Bricks will be a little slower to arrive as one type is in short supply. Brick layer booked in to start before Christmas.

Friday, November 23, 2012

Frame complete

The house frame is now up. I am amazed how accurate the frame is with hardly any bits leftover - nothing like an average piece of flatpack furniture.


Friday, November 16, 2012

Slab complete

Within the space of 9 work days, the block has been excavated to accommodate the slab, the slab has been poured and the Kordon termite protection has been laid.
Work has been happening on site each day.
We chose to have the earthmovers excavate the pool area and rear verandah area so we could easily continue the landscaping and pool installation after handover over the house.
excavations complete - 180 tons of soil to be removed later

slab poured