Friday, November 16, 2012

Slab complete

Within the space of 9 work days, the block has been excavated to accommodate the slab, the slab has been poured and the Kordon termite protection has been laid.
Work has been happening on site each day.
We chose to have the earthmovers excavate the pool area and rear verandah area so we could easily continue the landscaping and pool installation after handover over the house.
excavations complete - 180 tons of soil to be removed later

slab poured