Monday, February 18, 2013

A few more deliveries today

The gyprocker has been working steadily each day over the last week or so, including Saturday and Sunday. He applied 95% of the cornice today. Result looks great!
Other additions today include the delivery of water tank, manhole surround, all internal doors and frames, and skirting boards.



Water proofers booked in for tomorrow or Thursday.
We have settled on a carpet retailer, and they will contact site supervisor to complete a thorough measurement once skirtings are installed. Going for Arc Bamboo (champagne) and a Solution Dyed Nylon carpet in charcoal colour.
Our work on the block has continued, moving leftover bricks by wheelbarrow for use behind retaining walls. Probably a couple more weekends should knock over what is left.
We have decided to construct a gabian wall as part of the retaining wall system at the rear of the house. The leftover bricks shouls come in handy for this as well.